The critical path of a network is the A. path with the fewest activities. B. path with the most activities. C. shortest time path through the network. D. longest time path through the network.

Respuesta :

uzamamanzoor1271996 uzamamanzoor1271996
  • 24-02-2020

Answer:

D is correct option

Explanation:

D. longest time path through the network.

The sequence of activities within the network with zero total float is called critical path.

Answer Link

Otras preguntas

Drag each label to the correct location on the image. Identify these elements of photosynthesis.A) Light EnergyB) GlucoseC) Carbon Dioxide The image attached ha
HELP ME PLZZZ I really need the help with it
Why do you think portly was lost ? In wind in the willows
I still can't afford to fail this semester. The question is in the picture
Should we go to the early or late evening show?Either suit me
1. A company that produces bread is concerned about the distribution of the amount of sodium in its bread. The company takes a simple random sample of 100 slice
given quyens timeline below, which of the following events would prevent her from achieving her career goal on time as planned
How did the presence of Spanish missions in North America help Spain? Question 5 options: Adopted Native American rituals Brought more wealth to Spain Learned N
any thoughts?! I couldn't fix it
v. Which of the following is the superlative form of the word thirsty?(a) Thirsty(b) Thirstier(c) Thirstiest(d) Most thirsty​