during a consultation project,if a worker can lay 304 bricks in a day ,and 560 workers are worker ng on the project how many bricks will be laid in a week​

Respuesta :

Answer:

1,191,680

Explanation:

304 x 560 x 7 = 1,191,680

Answer:

560x304=170240x7=1191680 in one week

Explanation: idrk