a task completed by 30 persons in 4 days. in how many days, the same will be completed by 40 persons?

Respuesta :

Plasmataco
Plasmataco Plasmataco
  • 25-11-2017
Basically to solve this you do:
Time1*Worker1=Time2*Worker2
Thus Time1=4, Worker1=30, Worker2=40
4*30=40*Time2
Time2=4*30/40
Time2=3 days
Answer Link

Otras preguntas

What is the difference between Weight and Mass?Please give a fair amount of detail!
286,489 Is an odd number. How many times greater Is the 8 In the ten thousands place than the 8 In the tens place?
During February, Kevin will water his ivy every third day, and water his cactus every fifth day. On which date will Kevin first water BOTH plants together?
Self-fulfillment is associated with the development of one’s health and leisure habits. true or false?
How did neolithic people conduct trade?
the equation P=2(L +w) can be used to find the perimeter P of a rectangle with length L and width W. Solve the equation for w to produce a formula for finding t
tell how to find 81-16 using mental math
What is a distance across the middle of a circle or sphere?
Which individual from the Renaissance is known for writing The Divine Comedy using Italian rather than Latin?
Sari has 3 times as many pencil erasers as Sam. Together, they have 28 erasers. How many erasers does Sari have?